August 2022 Update

Share On

August was another busy month for Avalon Apartments, with the additional internal demolition work started. Confirming that the actual apartment fitouts will recommence in September. The first corner of the scaffold has been assembled, that will provide alternative access to the building for the construction team.


Progress has also been made on the actual site: preparation is underway for the ground floor’s exterior landscaping, and existing elements of the private road have been ripped up ready for installation of new pipes and laying of the car park pavement.


The inbound goods team managed the delivery of lift equipment, internal doors, floor coverings, insulation, and plumbing materials. Busy time onsite!


Programmed completion:


As communicated last month, we do need to reforecast completion due to the delay caused by additional demolition requirements. We will update you once the new milestones are confirmed and agreed by all parties.


Photo update: Below are a selection of photos, taken 18 August 2022:

 

 

North end landscape preparation.

 

 

South end landscape preparation.

 

 

West side civil works.

 

 

 

Ongoing contact:

If you have any questions at all, please contact your sales agent: 

 

Redcoats Professionals: shane@redcoats.co.nz or 021 459 622

The Wellington Company: Rakesh.Champaneri@twc.co.nz or 021 175 0490

 

 

Previous media
Previous media