JWA Developments Limited would like to share with our homeowners the current progress at Mabel Central.
Update on site progress
• Aluminium joinery installed in Block 1 as well as electrical and plumbing first fix.
• Block 1 exterior painting & cladding has begun.
• Block 9 mid floors, roof trusses and first level wall framing have been completed
• Block 7 & 8 panels have been erected
• Block 5 & 6 foundations are underway